Talixis Mining ServicesPrototype showcase ← The plant

First unit operation · Gravity plant

Grizzly feeder GF-3

The front end of our small-scale gold plant, designed to be built from Nigerian steel sections by a local welding workshop. It takes run-of-mine gravel by the barrow, washes it, rejects the stones, and meters an even feed into the 2 mm wash screen.

Prototype design, Rev A · not yet built
3 t/hrun-of-mine feed, design rate
25 mmbar gap: stones larger than this are rejected
1.1 m³hopper below the deck, about 35 minutes of feed
0 kWno motor: gravity, water and a hand wheel
Drag to turn · scroll or pinch to zoom

Whole unit. About 3 m high at the back edge of the deck, on a portable skid. About 1 tonne of mild steel.

150 mm

Where it sits in the plant

Every tonne the plant treats passes over this unit first. It does three jobs: it holds a buffer of ore so the plant runs evenly between barrow loads, it washes clay off the gravel, and it removes stones that would tear the screen mesh.

In our plant design the feed end was an imported mini grizzly. GF-3 replaces it with a unit any local workshop can build, repair and copy.

  1. 300-GZ-01Grizzly feederWash, reject stones over 25 mm, meter the feed
  2. 300-SC-01Wash screenSplit at 2 mm; oversize over the sluice
  3. 300-CN-01Centrifugal concentratorHolds gold and heavy minerals
  4. 400-TB-01Shaking tableUpgrades the concentrate
  5. 400-FU-01Smelt with boraxGold doré, no mercury

How it works

Four steps, all by gravity and water. Pick a step to see the part on the model.

Design basis and sizing

Sized from the plant's own design basis: 2 t an hour of screened feed to the concentrator, with 30% of the run-of-mine rejected as oversize, on one 10-hour shift at 85% availability.

ItemValueHow we got it
Run-of-mine feed2.86 → 3.0 t/h24.3 t a day over 8.5 working hours; designed for 3 t/h
Feed material≤ 300 mm lumpsAlluvial gravel and weathered ore, wet and clayey, free-digging
Bulk density1.6 t/m³Assumed for wet, loose gravel; to be measured on site
Grizzly deckabout 1.1 t/h per m²A light load that leaves room for sticky ore
Bar gap25 mmKeeps stones off the 2 mm screen mesh
Hopperabout 1.1 m³About 1.8 t, roughly 35 minutes of feed at 3 t/h
Waterabout 3 m³/hSpray bar about 2 m³/h and corner jets about 1 m³/h, drawn from the plant's recycled water and counted in its 7.1 m³/h slurry water
PowernoneGravity feed; the gate is set by a hand wheel
Steelabout 1 tMild-steel plate and standard sections

Design values for the prototype, Rev A. Throughput, blinding and water use are confirmed in the test plan below before the design is frozen.

Indicative arrangement, side elevation Side view of the grizzly feeder standing against a cut bank on the left. The grizzly deck slopes down at 25 degrees from about 3 metres at the back to the front, where oversize falls onto a chute. Below the deck the hopper narrows to an outlet with a slide gate and a discharge chute to the wash screen. Legs stand on a 2.4 metre skid. Cut bank or earth ramp: barrows tip here to 2 mm wash screen stones over 25 mm to the oversize stack spray bar 3.0 m 2.4 m skid 25°
Indicative arrangement, side elevation, Rev A. Overall dimensions only; not for construction.

Built locally

Everything on GF-3 is cut, drilled and welded from standard mild-steel sections sold in Nigerian steel markets. There are no machined parts, no motor and no imported wear parts, so a competent local welding workshop can build and repair it.

PartMade from
Hopper and side platesMild-steel plate
Grizzly barsFlat bar, bolted in replaceable sets
Frame and skidSteel angle and channel
Slide gateSteel plate, threaded rod and a hand wheel
Spray bar and corner jetsGalvanised pipe and ball valves
Impact linerUsed conveyor belt
  • Easy to repairBars bolt in as replaceable sets, and worn bars are swapped with stock flat bar.
  • Fits a containerThe deck and side plates unbolt, so the unit ships in a 20-foot container with the rest of the plant.
  • Rubber where rock hitsUsed conveyor belt lines the face where stones land, so the hopper wall is not worn through.
  • Safe by designThe 25 mm bars double as a fall guard. Nobody stands on the deck: oversize is raked from the bank, the gate wheel sits clear of the chute, and the gate is locked shut before anyone clears a hang-up.

Prototype test plan

The first unit is built in Osun State and tested on real run-of-mine ore before the design is frozen. Each test has a pass mark set from the design basis.

  1. Workshop check
    Trial fit, weld inspection and a water test of the spray bar and jets.
    Pass: no leaks; the gate runs its full travel by hand.
  2. Gate calibration
    Weigh the feed delivered in timed runs at each gate opening.
    Pass: a chart of tonnes an hour against gate opening, covering 1 to 4 t/h.
  3. Full-shift run
    Feed run-of-mine ore at 3 t/h for a 10-hour shift, logging every hang-up and rake.
    Pass: 3 t/h held through the shift with no blockage that stops the plant.
  4. Water use
    Meter the spray bar and corner jets during the shift.
    Pass: 3 m³/h or less in total.
  5. Wear check
    Measure bar and liner wear after 100 operating hours.
    Pass: wear rate gives at least one season before the bars are turned.